# Building (Prescribed Fees) Regulations (Northern Ireland) 1997, Schedule 3: Work other than work to which Schedule 1 or 2 apply

Extent: N.I.

Table to Schedule 3
Calculation of fees
Where the estimated cost does not exceed £2,000 the sum of
£60·00
Where the estimated cost exceeds £2,000 but does not exceed £5,000 the sum of
£150·00
Where the estimated cost exceeds £5,000 but does not exceed £20,000
(a) the sum of
£150·00
together with
(b) for every £1,000 (or part thereof) by which the cost exceeds £5,000, the sum of
£10·00
Where the estimated cost exceeds £20,000 but does not exceed £100,000
(a) the sum of
£300·00
together with
(b) for every £1,000 (or part thereof) by which the cost exceeds £20,000, the sum of
£8·00
Where the estimated cost exceeds £100,000 but does not exceed £1,000,000
(a) the sum of
£940·00
together with
(b) for every £1,000 (or part thereof) by which the cost exceeds £100,000, the sum of
£5·00
Where the estimated cost exceeds £1,000,000 but does not exceed £10,000,000
(a) the sum of
£5,440·00
together with
(b) for every £1,000 (or part thereof) by which the cost exceeds £1,000,000, the sum of
£3·50
Where the estimated cost exceeds £10,000,000
(a) the sum of
£36,940·00
together with
(b) for every £1,000 (or part thereof) by which the cost exceeds £10,000,000, the sum of
£3·00

---
Source: https://www.legislation.gov.uk/nisr/1997/482/schedule/3 (the official version)