# The Building (Registered Building Control Approvers etc.) (England) Regulations 2024, Regulation 11: Plans certificate

Extent: E+W

(1) The prescribed form of a plans certificate—
(a) which is not combined with an initial notice, is form 3 in Schedule 1; or
(b) which is combined with an initial notice, is form 4 in Schedule 1.
(2) The grounds on which a local authority must reject a plans certificate which is not combined with an initial notice are those prescribed in Schedule 3 and the form to be used for rejecting a plans certificate is form 7 in Schedule 1.
(3) The grounds on which a local authority must reject a plans certificate combined with an initial notice are those prescribed in Schedules 2 and 3 and the form to be used for rejecting a plans certificate is form 7 in Schedule 1.
(4) The period within which a local authority may give notice of rejection of a plans certificate (whether or not combined with an initial notice) is five working days beginning on the day on which the certificate is given.

---
Source: https://www.legislation.gov.uk/uksi/2024/110/regulation/11 (the official version)