# The Building (Registered Building Control Approvers etc.) (England) Regulations 2024, Paragraph 4: Capacity of approver

Extent: E+W

A new initial notice was in force with respect to the unfinished work described in the transfer certificate at the time the certificate was given, but—
(a) the certificate is not signed by the approver who gave the new initial notice,
(b) the person who signed the certificate is not an approver on the date the certificate is rejected, or
(c) where they are an approver, their registration does not include all the work described in the certificate.

---
Source: https://www.legislation.gov.uk/uksi/2024/110/schedule/5/paragraph/4 (the official version)