# The Building (Registered Building Control Approvers etc.) (Wales) Regulations 2024, Regulation 28: Form, grounds and period for rejecting public body’s plans certificate

Extent: E+W

(1) The prescribed form of a public body’s plans certificate—
(a) which is not combined with a public body’s notice, is Form PB2(W) in Schedule 1, or
(b) which is combined with a public body’s notice, is Form PB3(W) in Schedule 1.
(2) The grounds on which a local authority must reject a public body’s plans certificate are those prescribed in Schedule 7.
(3) The grounds on which a local authority must reject a public body’s plans certificate combined with a public body’s notice are those prescribed in Schedule 6 and Schedule 7.
(4) The period within which a local authority may give notice of rejection of a public body’s plans certificate or combined notice and certificate is 10 working days beginning on the day on which the certificate is given.

---
Source: https://www.legislation.gov.uk/wsi/2024/1268/regulation/28 (the official version)
Page: https://openlegislation.uk/building-registered-building-control-approvers-etc-wales-regulations-2024/regulation-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.