A local authority shall give a completion certificate in accordance with this regulation and as provided for in paragraph (2) where—

(a)

they receive a notice under regulation 15(4) or (5) that building work has been completed, or, that a building has been partly occupied before completion; and

(b)

they have either—

(i)

been notified, in accordance with regulation 14(4), that the building is put or is intended to be put to a use which is a relevant use as defined by regulation 12(1); or

(ii)

been requested, in accordance with regulation 14(5), to give a completion certificate.

(2)

Where in relation to any building work or, as the case may be, to any part of a building which has been occupied before completion, a local authority have been able to ascertain, after taking all reasonable steps, that the relevant requirements of Schedule 1 specified in the certificate have been satisfied, they shall give a certificate to that effect.

(3)

In this regulation “relevant requirements” mean—

(a)

in a case mentioned in paragraph (1)(b)(i), the applicable requirements of Part B of Schedule 1 (fire safety); and

(b)

in a case mentioned in paragraph (1)(b)(ii), any applicable requirements of Schedule 1.

(4)

A certificate given in accordance with this regulation shall be evidence (but not conclusive evidence) that the requirements specified in the certificate have been complied with.