Regulation 7 Transitional provision: HRB work - building control approval application for a stage of HRB work
(1)
This paragraph applies to HRB work on a particular building where a valid building control approval application for a stage of HRB work has been submitted to the regulator in relation to that building in accordance with regulation 4(3) (building control approval applications for HRB work or a stage of HRB work) of the HRB Regulations before 24th September 2027, provided that the application—
(a)
has not been rejected before that date; and
(b)
is not rejected on or after that date.
(2)
Where paragraph (1) applies, the amendments made by regulation 3 do not apply to any HRB work on the particular building.