# The Building Regulations (Northern Ireland) 2012, Regulation 67: Notification of testing and commissioning


Where this regulation applies, the person carrying out the work, for the purpose of ensuring compliance with regulation 65(2), shall give, not more than 5 days after completion of the testing and commissioning, a notice in writing to the district council stating—
(a) the results of air flow tests; and
(b) that any fixed mechanical ventilation system and associated controls have been commissioned.

---