# The Burbo Bank Extension Offshore Wind Farm Order 2014, Article 3: Development consent etc granted by the Order


(1) Subject to the provisions of this Order and to the Requirements, in Part 3 of Schedule 1, the undertaker is granted—
(a) development consent for the authorised development, in Part 1 of Schedule 1; and
(b) consent for the ancillary works, in Part 2 of Schedule 1,
to be carried out within the Order limits.
(2) Subject to the Requirements, the works comprised in the authorised development may be constructed anywhere within the Order limits.

---
Source: https://www.legislation.gov.uk/uksi/2014/2594/article/3 (the official version)
Page: https://openlegislation.uk/burbo-bank-extension-offshore-wind-farm-order-2014/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.