Paragraph 13 Community liaison
(1)
No installation of piled foundations shall commence until a community liaison scheme has been submitted to and approved by Wirral Metropolitan Borough Council.
(2)
The community liaison scheme shall include—
(a)
details of how the undertaker will liaise with the local community to ensure residents are informed of how the installation of the piled foundations is progressing;
(b)
a mechanism for dealing with complaints from the local community; and
(c)
a nominated representative of the undertaker who will have the lead role in liaising with local residents and Wirral Metropolitan Borough Council.
(3)
The undertaker shall comply with the approved community liaison scheme throughout the period during which piling is being undertaken.