# The Burbo Bank Extension Offshore Wind Farm Order 2014, Paragraph 5: Time limits


The total length of the cables comprising Work No. 1(b) must not exceed 65 kilometres and the total length of the cables comprising Work No. 3 must not exceed 17 kilometres.

---
Source: https://www.legislation.gov.uk/uksi/2014/2594/schedule/1/paragraph/5 (the official version)
Page: https://openlegislation.uk/burbo-bank-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.