Paragraph 6 Time limits

Original text. Later amendments are not shown.

(1)

Each steel monopile foundation forming part of the authorised development (excluding scour protection) shall not have a diameter which is greater than 8 metres.

(2)

Each gravity base foundation forming part of the authorised development (excluding scour protection) must not have—

(a)

a diameter at the level of the seabed which is greater than 35 metres;

(b)

in the case of the WTGs, a base height which is greater than 6 metres above the level of the seabed;

(c)

in the case of the offshore substation, a base height which is greater than 16 metres above the level of the seabed and less than 1 metre below LAT;

(d)

in the case of the WTGs, a column diameter of greater than 9 metres.

(3)

Each jacket foundation forming part of the authorised development (excluding scour protection) must not have—

(a)

a width spacing between each leg at the level of the seabed which is greater than 35 metres;

(b)

a leg diameter which is greater than 3 metres;

(c)

a width spacing between each leg at MHWS which is greater than 35 metres;

(d)

a pile sleeve height which is greater than 18 metres above the level of the seabed;

(e)

a pile diameter which is more than 3 metres;

(f)

more than one pile per leg, save in the case of the offshore substation where it shall not have more than four piles per leg;

(g)

more than four legs;

(h)

in the case of the offshore substation only, a suction caisson per leg which is greater than 15 metres in diameter.

(4)

To reduce potential impacts on adult salmon migration—

(a)

no more than 69 steel monopile foundations with a pile diameter of 6 metres or less (excluding scour protection) shall be installed as part of the authorised development;

(b)

no more than 65 steel monopile foundations with a pile diameter between 6 metres and 6.5 metres (excluding scour protection) shall be installed as part of the authorised development;

(c)

no more than 55 steel monopile foundations with a pile diameter between 6.5 metres and 7.5 metres (excluding scour protection) shall be installed as part of the authorised development;

(d)

no more than 45 steel monopile foundations with a pile diameter between 7.5 metres and 8 metres (excluding scour protection) shall be installed as part of the authorised development.