OpenLegislation

Paragraph 17 Piling restrictions

Original text. Later amendments are not shown.

(1)

Unless otherwise agreed in writing by the MMO in accordance with paragraph (2), no more than eight pin piles for the offshore substation jacket foundation shall be installed between 1 April and 15 May.

(2)

The undertaker shall submit a pin pile construction method statement to the MMO for approval showing the proposed numbers of piles to be installed and the estimated piling duration. If approved by the MMO, the installation must be carried out in accordance with the approved pin pile construction method statement.