Without prejudice to the generality of paragraph 2 above, the requirements which the Environment Agency may make under that paragraph include conditions requiring the Council at its own expense—
(a) to construct such protective works, whether temporary or permanent, during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—
(i) to safeguard any drainage work against damage, or
(ii) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased by reason of any specified work;
(b) to provide, maintain and operate a system of monitoring water quality in the harbour;
(c) to provide, maintain and operate arrangements for dealing with any pollution incidents which may occur.

---
Source: https://www.legislation.gov.uk/uksi/2000/2152/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/burry-port-harbour-revision-order-2000/schedule-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.