  "heading": "Retained apparatus: protection",
  "text": "(1) Not less than 56 days before commencing the execution of any authorised works that will or may affect any apparatus, the removal or diversion of which has not been required by the undertaker under paragraph 101(2) or otherwise or by the statutory undertaker under paragraph 6(3), the undertaker must submit to the statutory undertaker in question a plan showing the authorised works and the apparatus.\n(2) In relation to works which will or may be situated on, over, under or within 15 metres measured in any direction of any apparatus, or (wherever situated) impose any load directly upon any apparatus or involve embankment works within 15 metres of any apparatus, the plan to be submitted to the statutory undertaker under sub-paragraph (1) shall be detailed including a method statement and describing—\n(a) the exact position of the authorised works;\n(b) the level at which these are proposed to be constructed or renewed;\n(c) the manner of their construction or renewal including details of excavation, positioning of plant etc;\n(d) the position of all apparatus; and\n(e) by way of detailed drawings, every alteration proposed to be made to or close to any apparatus.\n(3) The Undertaker must not commence the construction or renewal of any authorised works to which sub-paragraphs (1) or (2) apply until the statutory undertaker has given written approval of the plan so submitted.\n(4) Any approval of the statutory undertaker required under sub-paragraph (3)—\n(a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5) or (7); and\n(b) shall not be unreasonably withheld or delayed.\n(5) In relation to works to which sub-paragraph (2) applies, the statutory undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.\n(6) Works executed under the Order to which this paragraph 8 applies shall be executed only in accordance with the relevant plan, notified under sub-paragraph (1) and approved (with conditions, if applicable) under sub-paragraph (4), as amended from time to time by agreement between the undertaker and the statutory undertaker. The statutory undertaker shall be entitled to watch and inspect the execution of those works.\n(7) Where the statutory undertaker requires any protective works or subsidence monitoring to be carried out either by itself or by the undertaker (whether of a temporary or permanent nature), the statutory undertaker must give the undertaker reasonable notice of such requirement in its approval under sub-paragraph (3), and\n(a) such protective works must be carried out to the statutory undertakers’ reasonable satisfaction prior to the carrying out of the relevant part of the authorised works;\n(b) ground subsidence monitoring shall be carried out in accordance with a scheme approved by the statutory undertaker (such approval not to be unreasonably withheld or delayed), which must set out:\n(i) the apparatus which is to be subject to such monitoring;\n(ii) the extent of land to be monitored;\n(iii) the manner in which ground levels are to be monitored;\n(iv) the timescales of any monitoring activities; and\n(v) the extent of ground subsidence which, if exceeded, requires the undertaker to submit for the statutory undertaker’s approval a ground subsidence mitigation scheme in respect of such subsidence;\n(c) if a subsidence mitigation scheme is required, it must be carried out as approved by the statutory undertaker (such approval not to be unreasonably withheld or delayed).\n(8) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the relevant authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.\n(9) The undertaker must not be required to comply with sub-paragraphs (1) or (2) where it needs to carry out emergency works as defined in the 1991 Act, but in that case it must give to the statutory undertaker notice as soon as is reasonably practicable and a plan of those works shall comply with the other requirements in this paragraph insofar as is reasonably practicable in the circumstances, provided that it always complies with sub-paragraph (11).\n(10) At all times when carrying out any works authorised under the Order that may or will affect the apparatus, the undertaker must comply with the statutory undertaker’s policies for safe working in proximity to gas apparatus including the “Specification for safe working in the vicinity of Northern Gas Networks, Gas pipelines and associated installation requirements for third parties “NGN/SPSSW22” and the Health and Safety Executive guidance document “HS(G)47 Avoiding Danger from underground services”.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 11 para. 103 in force at 14.8.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/934/schedule/11/paragraph/103",
    "retrieved_at": "2026-10-28T21:12:25.595636+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}