# The Byers Gill Solar Order 2025, Paragraph 42: Access

Extent: E+W

If in consequence of the agreement reached in accordance with paragraphs 34(1) and 34(2) or the powers granted under this Order the access to any apparatus and/or to the EGL1 Site is materially obstructed, the undertaker must provide such alternative means of access to such apparatus and/or to the EGL1 Site as will enable National Grid Electricity Transmission Plc to access, maintain or use the apparatus and/or the EGL1 Site no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2025/934/schedule/11/paragraph/42 (the official version)
Page: https://openlegislation.uk/byers-gill-solar-order-2025/schedule-11/paragraph-42
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.