# The Byers Gill Solar Order 2025, Paragraph 15: Construction hours

Extent: E+W

(1) Subject to sub-paragraph (2), no construction works are to take place except between the hours of—
(a) 08:00 to 18:00 Monday to Friday; and
(b) 08:00 to 13:00 on Saturday.
(2) With no activity on Sundays or bank holidays.
(3) The following works are permitted outside the hours referred to in sub-paragraph (1)—
(a) emergency works; and
(b) works which do not cause noise that is audible at the boundary of the Order limits.
(4) Any emergency works carried out under sub-paragraph (3)(a) must be notified to the relevant planning authority within 72 hours of their commencement.

---