# The Byers Gill Solar Order 2025, Paragraph 17: Fencing and other means of enclosure

Extent: E+W

(1) No phase of the authorised development may commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works for that phase have been submitted to and approved by the relevant planning authority as part of the detailed design approval required by requirement 3(1) (detailed design approval).
(2) For the purposes of paragraph (1), “commence” includes any site preparation works.
(3) Any construction site must remain securely fenced in accordance with the approved details at all times during construction of the authorised development.
(4) Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
(5) Any approved permanent fencing must be completed before completion of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/934/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/byers-gill-solar-order-2025/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.