# The Byers Gill Solar Order 2025, Paragraph 2: Phases of authorised development and date of final commissioning

Extent: E+W

(1) The authorised development may not be commenced until a written scheme setting out the proposed phases of construction of the authorised development has been submitted to and approved by the relevant planning authority.
(2) The scheme must be implemented as approved.
(3) Notice of the date of final commissioning in respect of the first phase of Work No. 1 must be given to the relevant planning authority within 15 working days of the date of final commissioning for that phase.
(4) Nothing shall prevent the undertaker and the relevant planning authority agreeing from time to time to amend the written scheme setting out the proposed phases of construction.
(5) The agreed written scheme may contain flexibility and optioneering for different proposed phases of construction provided that the undertaker notifies the relevant planning authority of the final intended phasing prior to commencement.

---
Source: https://www.legislation.gov.uk/uksi/2025/934/schedule/2/paragraph/2 (the official version)
Page: https://openlegislation.uk/byers-gill-solar-order-2025/schedule-2/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.