# The Byers Gill Solar Order 2025, Part 1: PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED

Extent: E+W

(1)
Area
(2)
Public right of way to be temporarily closed
(3)
Extent of temporary closure
Parish of Brafferton
Footpath No.7
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.7, comprising a length of 320m as shown between points marked 1 and 2 on sheet 1 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No. 8
Temporary management including temporary closure over the public right of way, referenced FP-Brn.8, comprising a length of 150m between points marked 1 and 3 on Sheet 1 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No. 9
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.9, comprising a length of 15m as shown between points marked 5 and 6 on sheet 1 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No.10
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.10, comprising a length of 50m as shown between points marked 7 and 8 on sheets 1 and 3 of the street works, public rights of way and access plans.
Parish of Brafferton
Bridleway No.14
Temporary management including temporary closure over the public right of way, referenced BR-Bfn.14, comprising a length of 1635m as shown between points 9 and 10 on sheet 3 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No.9
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.9, comprising a length of 613m as shown between points 11 and 11a on sheet 1 of the Street Works, Public Rights of Way and Access plans.
Parish of Brafferton
Footpath No.9
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.9, comprising a length of 135m as shown between points 11 and 12 on sheet 1 of the Street Works, Public Rights of Way and Access plans.
Parish of Brafferton
Footpath No.20
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.20, comprising a length of 50m as shown between points 13 and 14 on sheet 3 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No.15
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.15, comprising a length of 140m as shown between points 16 and 17 on sheet 4 of the street works, public rights of way and access plans.
Parish of Brafferton
Bridleway No.11
Temporary management including temporary closure over the public right of way, referenced BR-Bfn.11, comprising a length of 65m as shown between points 19 and 20 on sheet 4 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No.12
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.12, comprising a length of 260m as shown between points 21 and 22 on sheet 4 of the street works, public rights of way and access plans.
Parish of Brafferton
Footpath No. 12
Temporary management including temporary closure over the public right of way, referenced FP-Bfn.12, comprising a length of 80m as shown between points 23 and 24 on sheet 5 of the street works, public rights of way and access plans.
Parish of Brafferton
Bridleway No.13
Temporary management including temporary closure over the public right of way, referenced BR-Bfn.13, comprising a length of 55m as shown between points 25 and 26 on sheets 4 and 6 of the street works, public rights of way and access plans.
Parish of Great Stainton
Footpath No.4
Temporary management including temporary closure over the public right of way, referenced FP-GtStn.4, comprising a length of 315m as shown between points 27 and 28 on sheets 2 and 5 of the street works, public rights of way and access plans.
Parish of Great Stainton
Footpath No.6
Temporary management including temporary closure over the public right of way, referenced FP-GtStn.6, comprising a length of 300m as shown between points 29 and 30 on sheet 5 of the street works, public rights of way and access plans.
Parish of Great Stainton
Footpath No. 12
Temporary management including temporary closure over the public right of way, referenced FP-GtStn.12, comprising a length of 30m as shown between points 30 and 31 on sheet 5 of the street works, public rights of way and access plans.
Parish of Little Stainton
Footpath No.2
Temporary management including temporary closure over the public right of way, referenced FP-LtStn.2, comprising a length of 430m as shown between points 32 and 33 on sheet 6 of the street works, public rights of way and access plans.
Parish of Little Stainton
Footpath No.1
Temporary management including temporary closure over the public right of way, referenced FP-LtStn.1, comprising a length of 485m as shown between points 34 and 35 on sheets 6 and 7 of the street works, public rights of way and access plans.
Parish of Little Stainton
Footpath No.1
Temporary management including temporary closure over the public right of way, referenced FP-LtStn.1, comprising a length of 45m as shown between points 37 and 38 on sheet 7 of the street works, public rights of way and access plans.
Parish of Great Stainton
Footpath No.8
Temporary management including temporary closure over the public right of way, referenced FP-GtStn.8, comprising a length of 876m as shown between points 39 and 40 on sheets 7 and 8 of the street works, public rights of way and access plans.
Parish of Great Stainton
Footpath No.3
Temporary management including temporary closure over the public right of way, referenced FP-GtStn.3, comprising a length of 805m as shown between points 42 and 44 on sheet 8 of the street works, public rights of way and access plans.
Parish of Bishopton
Footpath No. 2
Temporary management including temporary closure over the public right of way, referenced FP-Btn.2, comprising a length of 960m as shown between points 45 and 46 on sheet 9 of the street works, public rights of way and access plans.
Parish of Bishopton
Footpath No.3
Temporary management including temporary closure over the public right of way, referenced FP-Btn.3, comprising a length of 60m as shown between points 47 and 48 on sheet 9 of the street works, public rights of way and access plans.
Parish of Bishopton
Footpath No. 4
Temporary management including temporary closure over the public right of way, referenced FP-Btn.4, comprising a length of 610m as shown between points 49 and 50 on sheets 10 and 11 of the street works, public rights of way and access plans.
Parish of Bishopton
Footpath No.7
Temporary management including temporary closure over the public right of way, referenced FP-Btn.7, comprising a length of 40m as shown between points 51 and 52 on sheet 11 of the street works, public rights of way and access plans.
Parish of Redmarshall
Footpath No.1
Temporary management including temporary closure over the public right of way, referenced FP-Rml.1, comprising a length of 40m as shown between points 53 and 54 on sheet 12 of the street works, public rights of way and access plans.
Parish of Redmarshall
Footpath No.2
Temporary management including temporary closure over the public right of way, referenced FP-Rml.2, comprising a length of 30m as shown between points 55 and 56 on sheet 12 of the street works, public rights of way and access plans.
Parish of Carlton
Footpath No.7
Temporary management including temporary closure over the public right of way, referenced FP-Ctn.7, comprising a length of 55m as shown between points 57 and 58 on sheets 12 and 13 of the street works, public rights of way and access plans.
Parish of Carlton
Footpath No.6
Temporary management including temporary closure over the public right of way, referenced FP-Ctn.6, comprising a length of 35m as shown between points 59 and 60 on sheets 12 and 13 of the street works, public rights of way and access plans.
Parish of Carlton
Traffic-free cycle route
Temporary management of the public right of way including temporary closure over a traffic-free cycle route, comprising a length of 15m as shown between points 63 and 64 on sheet 13 of the street works, public rights of way and access plans.

---
Source: https://www.legislation.gov.uk/uksi/2025/934/schedule/5/part/1 (the official version)