# The Cableway Installations Regulations 2018, Regulation 5: Cableway installations: duties of the main contractor


(1) A person must not carry out or permit to be carried out works for the construction or modification of a cableway installation otherwise than under and in accordance with a stage 1 authorisation.
(2) The main contractor is responsible for carrying out the safety analysis and preparing the safety report required under Article 8 of Regulation 2016/424/EU.
(3) The instruction manual and the corresponding notes relating to the cableway installation must be drawn up in English.
(4) For the purposes of paragraph (1), a stage 1 authorisation includes a stage 1 authorisation given by the Secretary of State under regulation 13(1) of the Cableway Installations Regulations 2004 before the date on which these Regulations come into force.

---
Source: https://www.legislation.gov.uk/uksi/2018/816/regulation/5 (the official version)