(1)

Subject to paragraph (2), if the works authorised by this Order are not substantially completed within ten years from the coming into force of this Order or such extended time as the Ministers may on the application of CMAL allow, then on the expiration of that period or such extended time (as the case may be) the powers by this Order granted to CMAL for making and maintaining the works shall cease except as to so much of those works as are then substantially commenced.

(2)

Nothing in paragraph (1) shall apply to any works carried out under article 5 (subsidiary works) or under article 3(4).