# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Schedule 12: LAND OF WHICH TEMPORARY POSSESSION ONLY MAY BE TAKEN


(1) Area
(2) Number of land shown on land plan
(3) Purpose of which temporary possession may be taken
(4) Relevant site or part of the authorised development
Cambridge City Council
005h, 005i
The siting of and operation of apparatus for monitoring vibration, ground movement and other construction impacts in the vicinity of the operational railway, and access for the same.
Decommissioning activities and access for the same.
Work Nos. 30 and 40
Cambridge City Council
008d, 008f, 012h
The siting of and operation of apparatus for monitoring vibration, ground movement and other construction impacts in the vicinity of the operational railway, and access for the same.
Work No. 30
South Cambridgeshire District Council
021g
Construction worksite, compound, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials.
Creation of temporary haul roads, laying of hardstanding and improvements to means of access.
Erection of associated temporary structures, siting of a crane, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Mud and soil handling, earthworks, ground re-profiling, vegetation clearance, dewatering, construction and commission drainage and discharge.
Work Nos. 28 and 29
South Cambridgeshire District Council
021i
Construction worksite, compound, horizontal directional drilling work area, area for the stringing out of pipelines, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials.
Creation of temporary haul roads, laying of hardstanding and improvements to means of access.
Erection of associated temporary structures, siting of a crane, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Mud and soil handling, earthworks, ground re-profiling, vegetation clearance, dewatering, construction and commission drainage and discharge.
Work Nos. 28, 29 and 34
South Cambridgeshire District Council
022l, 022m, 022n, 022o, 024a, 024b, 034g
Worksite, landscaping and ecological works, signage.
Access, with or without vehicles, plant, machinery and materials.
Ground re-profiling and vegetation clearance.
Work No. 1
South Cambridgeshire District Council
036d, 039b, 042b, 044b
Construction worksite, compound, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials.
Creation of temporary haul roads, laying of hardstanding and improvements to means of access.
Erection of associated temporary structures, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Mud and soil handling, earthworks, ground re-profiling, vegetation clearance, dewatering, construction and commission drainage and discharge.
Work No. 34
South Cambridgeshire District Council
030a
Worksite, landscaping and ecological works, signage.
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to means of access.
Dewatering, construction and commission drainage and discharge.
Work Nos. 1, 23, 24 and 37
South Cambridgeshire District Council
031a
Worksite, landscaping and ecological works, signage.
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to means of access.
Work No. 23
South Cambridgeshire District Council
031b
Worksite, landscaping and ecological works, signage.
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to means of access.
Dewatering, construction and commission drainage and discharge.
Work Nos. 22, 23 and 37
South Cambridgeshire District Council
031c, 034b
Worksite, landscaping and ecological works.
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to means of access.
Dewatering, construction and commission drainage and discharge.
Work Nos. 1, 21, 22, 23 and 37
South Cambridgeshire District Council
038e
Construction worksite, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to means of access.
Erection of associated temporary structures, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Mud and soil handling, earthworks, ground re-profiling, vegetation clearance, dewatering, construction and commission drainage and discharge.
Work Nos. 1, 21, 22, 23 and 37
South Cambridgeshire District Council
042c, 042f, 044c, 046c, 046d, 047c, 047e, 058b, 058c, 065c
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to the means of access.
Dewatering, construction and commission drainage and discharge.
Work No. 37
South Cambridgeshire District Council
056b
Construction worksite, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials, improvements to means of access.
Erection of associated temporary structures, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Dewatering, construction and commission drainage and discharge.
Work No. 37
South Cambridgeshire District Council
060c
Construction worksite, compounds, horizontal directional drilling work area, area for the stringing out of pipelines, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials.
Creation of temporary haul roads, laying of hardstanding and improvements to means of access.
Erection of associated temporary structures, siting of a crane, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Mud and soil handling, earthworks, ground re-profiling, vegetation clearance, dewatering, construction and commission drainage and discharge.
The siting of and operation of apparatus for monitoring vibration, ground movement and other construction impacts in the vicinity of the operational railway, and access for the same.
Work Nos. 30 and 34
South Cambridgeshire District Council
060d, 074a, 074b
The siting of and operation of apparatus for monitoring vibration, ground movement and other construction impacts in the vicinity of the operational railway, and access for the same.
Work No. 30
South Cambridgeshire District Council
070a, 071a
Construction worksite, compound, storage, welfare and laydown area.
Access, including parking, with or without vehicles, plant, machinery and materials.
Creation of temporary haul roads, laying of hardstanding and improvements to means of access.
Erection of associated temporary structures, siting of a crane, storage of equipment and connection of utilities services, including fencing, security, lighting, welfare requirements and signage.
Mud and soil handling, earthworks, ground re-profiling, vegetation clearance, dewatering, construction and commission drainage and discharge.
Work No. 34

---
Source: https://www.legislation.gov.uk/uksi/2025/452/schedule/12 (the official version)
Page: https://openlegislation.uk/cambridge-waste-water-treatment-plant-relocation-order-2025/schedule-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.