# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Part 12: CAKE DEWATERING AND STORAGE (WORK No. 8)


(1) Item
(2) Number
(3) Maximum design parameter
(4) Maximum height
Finished ground level (+ or – 0.5m)
–
–
9m AOD
Cake storage barn or silo
1
30m x 40m
18m AOD (9m above FGL)
Dewatering centrifuges/volutes
2
20m x 20m
Gantry height 17m AOD (8m above FGL)
Foundation depth
Piles to a depth of -16m AOD (25m below FGL)
Overall footprint of dewatering and cake storage area
–
60m x 50m (9m above FGL)

---
Source: https://www.legislation.gov.uk/uksi/2025/452/schedule/14/part/12 (the official version)