# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Part 14: NUTRIENT RECOVERY OPTION (WORK No. 8)


(1) Item
(2) Maximum design parameter
Finished ground level (+ or – 0.5m)
9m AOD
Number of stripping/scrubbing columns
3 No.
Stripping/scrubbing column heights
27m AOD (18m above FGL)
Stripping/scrubbing column diameters
3m
Feed pumping station – depth
4m AOD (5m below FGL)
Foundation depth
Piles to a depth of -16m AOD (25m below FGL)
Total Area
50m x 50m
Total height
27m AOD (18m above FGL)

---
Source: https://www.legislation.gov.uk/uksi/2025/452/schedule/14/part/14 (the official version)