# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Paragraph 96: CDM Regulations


The undertaker shall assume the obligations of the client for the purposes of the CDM Regulations and shall ensure that the execution of the specified works complies with the CDM Regulations and in the course of carrying out those obligations the undertaker shall act as principal designer and appoint a principal contractor in respect of the specified works in accordance with the CDM Regulations.

---
Source: https://www.legislation.gov.uk/uksi/2025/452/schedule/15/paragraph/96 (the official version)
Page: https://openlegislation.uk/cambridge-waste-water-treatment-plant-relocation-order-2025/schedule-15/paragraph-96
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.