# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Paragraph 98: Commuted sum and asset fees


(1) If a commuted sum is required by the local highway authority the undertaker will pay the agreed commuted sum to the local highway authority prior to commencement of the part of the specified works to which the commuted sum relates.
(2) The undertaker shall pay the asset management fee and the asset planning fee to the local highway authority prior to commencement of the specified works.

---