# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Paragraph 19: Operational logistics traffic plan


(1) Prior to the operation of the authorised development a detailed operational logistics traffic plan must be submitted to and approved in writing by the relevant planning authority.
(2) The detailed operational logistics traffic plan submitted for approval must accord with the measures set out in the outline operational logistics traffic plan and must include—
(a) details of HGV delivery times; and
(b) HGV routeing and monitoring proposals.
(3) The detailed operational logistics traffic plan may be revised from time to time in accordance with requirement 6.
(4) The operation of the authorised development must be in accordance with the approved detailed operational logistics traffic plan.

---
Source: https://www.legislation.gov.uk/uksi/2025/452/schedule/2/paragraph/19 (the official version)
Page: https://openlegislation.uk/cambridge-waste-water-treatment-plant-relocation-order-2025/schedule-2/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.