# The Cambridge Waste Water Treatment Plant Relocation Order 2025, Part 1: PUBLIC RIGHTS OF WAY TO BE TEMPORARILY STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED


(1) Area
(2) Public right of way to be temporarily stopped up
(3) Extent of temporary diversion
(4) Stage of the authorised development
South Cambridgeshire District Council
Footpath FP85/6 north of the A14 shown with a wavy red line between points R1 and R2 on sheet 2 of the rights of way plans (Document number 4.6.2 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R1 and R2 on sheet 2 of the rights of way plans (Document number 4.6.2 as described in column (2) of Schedule 18)
During the carrying out of Work Nos. 31, 32 and 39
South Cambridgeshire District Council
Footpath FP130/6 south-east of the layby on Clayhithe Road shown with a wavy red line between points R3 and R4 on sheet 8 of the rights of way plans (Document number 4.6.8 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R3 and R4 on sheet 8 of the rights of way plans (Document number 4.6.8 as described in column (2) of Schedule 18)
During the carrying out of Work Nos. 33 and 34
South Cambridgeshire District Council
Bridleway 130/8 north-east of the layby on Clayhithe Road shown with a wavy red line between points R5 and R6 on sheet 8 of the rights of way plans (Document number 4.6.8 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R5 and R6 on sheet 8 of the rights of way plans (Document number 4.6.8 as described in column (2) of Schedule 18)
During the carrying out of Work Nos. 33 and 34
South Cambridgeshire District Council
Footpath FP130/10 east of Grange Farm shown with a wavy red line between points R7 and R8 on sheet 8 of the rights of way plans (Document number 4.6.8 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R7 and R8 on sheet 8 of the rights of way plans (Document number 4.6.8 as described in column (2) of Schedule 18)
During the carrying out of Work No. 33
South Cambridgeshire District Council
Footpath FP130/16 south-east of Riverside Farm shown with a wavy red line between points R9 and R10 on sheet 9 of the rights of way plans (Document number 4.6.9 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R9 and R10 on sheet 9 of the rights of way plans (Document number 4.6.9 as described in column (2) of Schedule 18)
During the carrying out of Work No. 33
South Cambridgeshire District Council
Footpaths FP130/12 and FP130/16 across Hatridge’s Lane and through Riverside Farm shown with a wavy red line between points R11 and R12 on sheet 9 of the rights of way plans (Document number 4.6.9 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R11 and R12 on sheet 9 of the rights of way plans (Document number 4.6.9 as described in column (2) of Schedule 18)
During the carrying out of Work Nos. 33 and 37
South Cambridgeshire District Council
Footpath FP247/10 north of the river Cam and south of Burgess’s Drove shown with a wavy red line between points R13 and R14 on sheet 9 of the rights of way plans (Document number 4.6.9 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R13 and R14 on sheet 9 of the rights of way plans (Document number 4.6.9 as described in column (2) of Schedule 18)
During the carrying out of Work No. 33
South Cambridgeshire District Council
Footpath FP85/8 north of the A14 shown with a wavy red line between points R15 and R16 on sheet 2 of the rights of way plans (Document number 4.6.2 as described in column (2) of Schedule 18)
The route shown indicatively with orange dots between points R15 and R16 on sheet 2 of the rights of way plans (Document number 4.6.2 as described in column (2) of Schedule 18)
During the carrying out of Work No. 31

---
Source: https://www.legislation.gov.uk/uksi/2025/452/schedule/6/part/1 (the official version)
Page: https://openlegislation.uk/cambridge-waste-water-treatment-plant-relocation-order-2025/schedule-6/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.