# The Carbon Capture Readiness (Electricity Generating Stations) (Amendment) (Wales) Regulations 2019, Regulation 3: Interpretation


In regulation 2(1) (interpretation) at the appropriate places insert the following definitions—
““the 1990 Act” means the Town and Country Planning Act 1990;”;
““devolved combustion plant” means a combustion plant in Wales with a related electrical output of between 300 and 350 megawatts;”;
““local planning authority” and “planning permission” have the meanings given in section 336 of the 1990 Act;”;
““relevant planning authority” means in relation to a relevant planning permission—
(a) where the development to which the application relates is of national significance for the purposes of section 62D of the 1990 Act, the Welsh Ministers;
(b) in all other cases, the local planning authority;”;
““relevant planning permission” means a planning permission—
(a) for the construction of a devolved combustion plant; or
(b) for an extension or alteration to a combustion plant in Wales which will have the effect of increasing the rated electrical output of the plant to between 300 and 350 megawatts;”.

---
Source: https://www.legislation.gov.uk/wsi/2019/294/regulation/3 (the official version)
Page: https://openlegislation.uk/carbon-capture-readiness-electricity-generating-stations-amendment-wales-regulations-2019/regulation-3