OpenLegislation

Paragraph 12

Original text. Later amendments are not shown.

For the purposes of this Part—

  • “contingency sum” means the contingency sum included in a fund estimate in accordance with paragraphs 6 to 10 of this Schedule;

  • “fully revised fund estimate” means a fund estimate for which all decommissioning cost categories and assumptions have been reviewed;

  • “material change” means a change during the fund operational period affecting the facts or assumptions underpinning an approved fund estimate (including a change to the technical, market or legal assumptions), that the Secretary of State has determined under paragraph 17 that it is, or may be, a material change, based on the matters in paragraph 19;

  • “partially revised fund estimate” means a fund estimate in respect of which specific, but not all, decommissioning cost categories, assumptions, infrastructure estimates or other discrete elements have been reviewed;

  • “periodic review period” means the six month period that begins with the day that is twelve months before and ends on the day that is six months before the periodic review date.