During the post operations period, a relevant person must submit a fully revised fund estimate, for all outstanding decommissioning actions yet to be carried out, to the Secretary of State for approval—
(a) no later than six months after the last day of the fund operational period, unless the Secretary of State agrees in writing that a later date may apply,
(b) on every 5th anniversary after the submission of the revised fund estimate under sub-paragraph (a).

---