Paragraph 4
Where there is a decommissioning cost that will be applicable to more than one infrastructure estimate (“shared decommissioning cost”)—
each relevant infrastructure estimate must include an appropriate proportion of the shared decommissioning cost,
there must be sufficient explanation and evidence to explain the method for the apportionment of costs, based on the extent to which the shared decommissioning cost is relevant to the infrastructure estimate, and
the sum of all proportions of a shared decommissioning cost—
must equal the total amount of the shared decommissioning cost, and
the total amount must be framed so as to ensure (whether by means of the timing of the measures proposed, the inclusion of provision for collaboration with other persons, or otherwise) that the cost of decommissioning is kept to the minimum that is reasonably practicable in the circumstances.