# The Carbon Dioxide Transport and Storage (Financing of Costs of Offshore Decommissioning) Regulations 2026, Paragraph 5


(1) A fund estimate and revised fund estimate, and each infrastructure estimate included within a fund estimate or revised fund estimate, must provide a breakdown of decommissioning costs, estimated in nominal terms and based on reasonable forecasts and assumptions, relating to covered offshore infrastructure.
(2) The breakdown of decommissioning costs must include each of the following categories of decommissioning actions—
(a) monitoring of the storage site after closure, in accordance with paragraph 2 of Schedule 2 to the applicable Licensing Regulations,
(b) reporting the monitoring results to the relevant regulator, in accordance with the applicable Licensing Regulations,
(c) preparatory work occurring after the cessation of transport and storage activity, that is proposed to take place prior to the carrying out of an abandonment programme,
(d) abandonment of the site including sealing the storage site and removal of the injection facilities in accordance with an abandonment programme,
(e) abandonment of carbon storage installations not captured by paragraph (d) and submarine pipelines in accordance with an abandonment programme,
(f) continuing inspection, monitoring and maintenance of any covered offshore infrastructure that is not removed, until the date the last financial contribution is paid in respect of a storage site covered under the section 7 licence,
(g) environmental surveys conducted after a storage site has been closed and reporting of potential remedial works in accordance with an abandonment programme,
(h) the financial contribution for each storage site covered under the section 7 licence,
(i) costs relating to the provision of insurance cover for risks relating to a closed storage site or for other risks properly attributable to decommissioning obligations (including contributions required under insurance provided pursuant to the exercise of the Secretary of State’s powers to provide financial assistance under section 129 of the 2023 Act),
(j) rent arising during the post operations period, under a lease or authorisation to exercise rights granted by the Crown Estate, or the Crown Estate Scotland, in respect of that storage site,
(k) administration costs, overheads and expenses (including statutory fees or levies) to be incurred by the relevant person where these are properly attributable to matters in paragraphs (a) to (j),
(l) post operations fund administration costs, and
(m) a proposed contingency sum in accordance with paragraphs 6 to 8 and paragraph 10 of this Schedule.
(3) The estimate must include an individual cost for each category of decommissioning costs listed in sub-paragraph (2), as well as a total figure for all the decommissioning costs.
(4) An estimate under this Schedule must, where applicable—
(a) incorporate information submitted under Part 4 of the 1998 Act, or submitted in a post-closure plan, or provisional post-closure plan, under the Licensing Regulations;
(b) explain any differences between information submitted as mentioned in paragraph (a) and the information submitted for the purposes of a fund estimate.
(5) A revised fund estimate under this Schedule does not need to include an estimate for the costs of a decommissioning action once that action has been carried out and completed.

---
Source: https://www.legislation.gov.uk/uksi/2026/632/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/carbon-dioxide-transport-and-storage-financing-of-costs-of-offshore-decommissioning-regulations-2026/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.