A fund estimate and revised fund estimate must include a proposed contingency sum (“contingency sum”) that must take into account—
potential future inflation that is in excess of the inflation assumptions in the fund accrual profile,
other forms of market volatility affecting assumptions underpinning the fund estimate or fund accrual profile,
works or other actions being required beyond those planned for in the work breakdown,
the range of decommissioning actions and variability of associated costs, due to known uncertainties, such as environmental conditions in different parts of the seabed, or weather conditions,
evolving experience in offshore carbon dioxide transport and storage activities, both in the United Kingdom and elsewhere, and
the risks attached to different decommissioning cost categories, or decommissioning actions.