# The Carbon Dioxide Transport and Storage (Financing of Costs of Offshore Decommissioning) Regulations 2026, Paragraph 6


The fund accrual profile and any separate accrual profile required under paragraph 5 must be consistent with—
(a) either—
(i) the approved fund estimate, including applicable infrastructure estimates, or
(ii) where a first fund estimate has been submitted under regulation 5(1), but not yet approved, the submitted estimate, and
(b) the accounting principle in regulation 26(2)(a).

---