# The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014, Article 40: Procedure in relation to approvals, etc., under Schedule 2

Extent: E+W+S

(1) Where an application is made to the relevant planning authority for any consent, agreement or approval required by a requirement under Schedule 2 (requirements), the following provisions apply in respect of that application as they would apply if that consent, agreement or approval were required by a condition imposed on a grant of planning permission—
(a) sections 78 (right to appeal against planning decisions and failure to take such decisions) and 79 (determination of appeals) of the 1990 Act; and
(b) any orders, rules or regulations which make provision in relation to a consent, agreement or approval of a local planning authority required by a condition imposed on the grant of planning permission.
(2) For the purposes of paragraph (1), a provision relates to a consent, agreement or approval of a local planning authority required by a condition imposed on a grant of planning permission in so far as it makes provision in relation to an application for such a consent, agreement or approval, or the grant or refusal of such an application, or a failure to give notice of a decision on such an application.

---
Source: https://www.legislation.gov.uk/uksi/2014/2637/article/40 (the official version)