Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference, the undertaker must not otherwise than by agreement with National Grid—
(a) acquire by compulsion from National Grid any right or interest in land (including rights in the subsoil of or the air-space over land) or any of National Grid’s apparatus, or impose restrictive covenants affecting land in which National Grid has rights or interests, or enter upon land, or override any wayleave, easement or other rights or interests of National Grid; or
(b) take temporary possession of any land that is not a highway so as to interfere with any easement, wayleave or other right relating to National Grid’s apparatus.

---
Source: https://www.legislation.gov.uk/uksi/2014/2637/schedule/10/paragraph/9 (the official version)