# The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014, Paragraph 12

Extent: E+W+S

(1) No part of the authorised development is to commence until a scheme of the lighting to be erected along the link road has been submitted to and approved in writing by the relevant planning authority.
(2) The scheme submitted under sub-paragraph (1) must include details of—
(a) the areas of the link road to be lit;
(b) the position of the lighting columns and their heights and designs, including their luminaires and any shielding that is to be incorporated into the lighting columns;
(c) the extent of the light spread from each column; and
(d) mitigation measures relating to lighting reflecting the proposals in the environmental statement.
(3) The authorised development must be carried out in accordance with the scheme approved under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2014/2637/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/central-bedfordshire-council-woodside-link-houghton-regis-development-consent-order-2014/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.