# The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014, Paragraph 18

Extent: E+W+S

(1) No part of the authorised development is to be opened for public use until a written scheme for monitoring the following effects of the authorised development has been submitted to and approved in writing by the relevant planning authority—
(a) effects on nature conservation interests;
(b) effects on access to community and private assets;
(c) effects on the water environment including water quality, hydrology and flood risk;
(d) landscape and visual effects;
(e) effects on air quality; and
(f) noise and vibration effects.
(2) The monitoring scheme must cover the monitoring of the above effects of the authorised development and their mitigation as set out in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2014/2637/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/central-bedfordshire-council-woodside-link-houghton-regis-development-consent-order-2014/schedule-2/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.