# The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014, Paragraph 4

Extent: E+W+S

(1) No part of the authorised development is to commence until detailed design documents have been approved by the relevant planning authority.
(2) Except as provided for by sub-paragraph (3), the authorised development must be carried out in accordance with the approved development plans and the landscaping plans.
(3) Replacement landscaping plans may be approved in writing by the relevant planning authority and substituted for the landscaping plans, provided that such approval is not given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement, and falls within the Order limits.

---
Source: https://www.legislation.gov.uk/uksi/2014/2637/schedule/2/paragraph/4 (the official version)
Page: https://openlegislation.uk/central-bedfordshire-council-woodside-link-houghton-regis-development-consent-order-2014/schedule-2/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.