The works referred to in this Order and shown on the deposited plan marked “The Central Regional Council (Kirkton Burn, Balquhidder) Water Order 1988 Plan and Sections of Works” are—
Work No. 1
River training works incorporating a weir with crest level 0.3 metres or thereby above the general bed level of the Kirkton Burn situated at a point 1,250 metres or thereby measured in a straight line north-north-west of kirkton Bridge where the Kingshouse to Balquhidder road crosses the said Kirkton Burn.
Work No. 2
An intake weir with crest level 0.1 metres or thereby above the general bed level of the said Kirkton Burn and a gauging chamber incorporating an approved gauge, situated immediately to the east of Work No. 1.
Work No. 3
A pipe to give residual flow in the said Kirkton Burn leading south from Work No. 2 for a distance of 20 metres or thereby.
Work No. 4
A chamber with approved gauge and a pipe extending 3 metres or thereby from the said chamber north-westwards to Work No. 2.

---
Source: https://www.legislation.gov.uk/uksi/1988/222/schedule/1 (the official version)
Page: https://openlegislation.uk/central-regional-council-kirkton-burn-balquhidder-water-order-1988/schedule-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.