Where any development to which any planning permission granted by virtue of section 9(4) of this Act relates consists of or includes the carrying out on any working site within the limits of land to be acquired of operations ancillary to any of the Railways Board’s works—
(a) those operations shall be discontinued before the end of the period of ten years beginning with the date of the passing of this Act; and
(b) the Railways Board shall, in accordance with a scheme agreed, in the case of a working site in a London borough, with the borough planning authority and, in the case of a working site anywhere else, by the district planning authority or, in default of agreement or on notice being given by the Secretary of State to the authority and the Railways Board, settled by him, put the site, except any part which is required for any of the Railways Board’s works, into such a condition as the scheme may provide.

---
Source: https://www.legislation.gov.uk/ukpga/1987/53/schedule/3/paragraph/16 (the official version)
Page: https://openlegislation.uk/channel-tunnel-act-1987/schedule-3/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.