# Channel Tunnel Act 1987, Paragraph 18


A planning authority shall not be required to entertain any request for an approval required for the purposes of any provision of this Schedule unless the Concessionaires have deposited with them both—
(a) a plan showing the Concessionaires’ current proposals regarding the layout of the authorised development; and
(b) a schedule setting out the Concessionaires’ current proposals regarding the timetable for carrying it out.

---
Source: https://www.legislation.gov.uk/ukpga/1987/53/schedule/3/paragraph/18 (the official version)
Page: https://openlegislation.uk/channel-tunnel-act-1987/schedule-3/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.