# Channel Tunnel Act 1987, Paragraph 17


(1) Any difference arising between the appropriate authority and the undertakers under this Part of this Schedule shall be determined by arbitration.
(2) In determining any such difference the arbitrator may, if he thinks fit, require the appropriate authority to carry out any temporary or other works so as to avoid, so far as may be reasonably possible, interference with the use of any apparatus.

---
Source: https://www.legislation.gov.uk/ukpga/1987/53/schedule/7/part/VI/paragraph/17 (the official version)
Page: https://openlegislation.uk/channel-tunnel-act-1987/schedule-7/part-VI/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.