# Channel Tunnel Rail Link Act 1996, Paragraph Work No. 15C


Realignment of Egerton Road, including a bridge over the railways (Works Nos. 15, 15A and 15B), commencing in that road at a point 5 metres south-west of the southern end of the bridge carrying it over the M20, passing north-eastwards over those railways and terminating in Egerton Road at a point 130 metres north-east of its junction with Vicarage Lane;

---
Source: https://www.legislation.gov.uk/ukpga/1996/61/schedule/1/crossheading/description-of-works/paragraph/Workn216 (the official version)
Page: https://openlegislation.uk/channel-tunnel-rail-link-act-1996/schedule-1/crossheading-description-of-works/paragraph-Workn216
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.