# Channel Tunnel Rail Link Act 1996, Paragraph Work No. 15F


Realignment of Newlands Road (D1199), including a bridge over the railway (Work No. 15), commencing in that road at a point 15 metres north of the northern abutment of the bridge carrying that road over the M20, passing northwards over the railway, then north-eastwards and terminating in Newlands Road at a point 135 metres north-east of its junction with Hurst Lane;

---
Source: https://www.legislation.gov.uk/ukpga/1996/61/schedule/1/crossheading/description-of-works/paragraph/Workn219 (the official version)
Page: https://openlegislation.uk/channel-tunnel-rail-link-act-1996/schedule-1/crossheading-description-of-works/paragraph-Workn219