# Channel Tunnel Rail Link Act 1996, Paragraph Work No. 22A


A railway (2,201 metres in length), forming a diversion of the Tilbury Loop Railway westbound line, commencing by a junction with that railway at a point 253 metres east of the junction of Stebbing Way with Wivenhoe Road, passing eastwards under Renwick Road, then south-eastwards and eastwards over the railway in tunnel (Work No. 22), under the new road (Work No. 22H(1)) and terminating by a junction with the Tilbury Loop Railway westbound line at a point 2 metres west of the western end of Dagenham Dock Station platforms;

---
Source: https://www.legislation.gov.uk/ukpga/1996/61/schedule/1/crossheading/description-of-works/paragraph/Workn81 (the official version)
Page: https://openlegislation.uk/channel-tunnel-rail-link-act-1996/schedule-1/crossheading-description-of-works/paragraph-Workn81
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.