# Channel Tunnel Rail Link Act 1996, Paragraph Work No. 22G


A railway (715 metres in length), for construction purposes, commencing by a junction with the railway (Work No. 22B) at a point 27 metres west of the point where the new road (Work No. 22H(1)) passes over Work No. 22B, passing eastwards then southwards, and terminating at a point 270 metres south-east of the eastern end of Dagenham Dock Station platforms, including railway sidings;

---
Source: https://www.legislation.gov.uk/ukpga/1996/61/schedule/1/crossheading/description-of-works/paragraph/Workn87 (the official version)
Page: https://openlegislation.uk/channel-tunnel-rail-link-act-1996/schedule-1/crossheading-description-of-works/paragraph-Workn87
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.