A planning authority shall not be required to entertain a request for approval under Part II or III of this Schedule unless—
(a) the nominated undertaker has deposited with the authority a document setting out its proposed programme with respect to the making of requests under that Part to the authority, and
(b) the request is accompanied by a document explaining how the matters to which the request relates fit into the overall scheme of the works authorised by this Part of this Act.

---