# The Channel Tunnel Rail Link (Stratford Station and Subsidiary Works) Order 2001, Article 4: Stopping up of highways


(1) Union Railways may exercise the power conferred by paragraph 1(1) of Schedule 3 to the principal Act to stop up York Way between points L1 and L2 (which points are shown on the deposited plans)—
(a) for the relevant purposes, and
(b) in relation to that part of York Way within the London Borough of Islington as well as the part within the London Borough of Camden.
(2) Paragraph (1) above has effect without prejudice to article 15(2) below and subject to paragraph 1(3) of Schedule 3 to the principal Act.
(3) In paragraph (1) above, “the relevant purposes” means purposes connected with the construction of the authorised works or the works authorised by Part I of the principal Act.

---
Source: https://www.legislation.gov.uk/uksi/2001/1451/article/4 (the official version)
Page: https://openlegislation.uk/channel-tunnel-rail-link-stratford-station-and-subsidiary-works-order-2001/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.